Elida WWTP
(CMAR)
- Owner: Village of Elida
- Contract Type: Construction Manager at Risk
- Contract Value: $10.9 Million
- Completion: May 2026
PCC was selected and awarded a contract for this CMAR project in 2023. Scope of the work included replacement of most of the treatment units at the WWTP including an anaerobic tank, (3) channel oxidation ditch, (2) final clarifiers, UV upgrades, post-aeration tanks, (2) solids holding tanks complete with blowers and pumps, a combined RAS/electrical/chemical feed building, and all associated Civil/MEP/Integration work. PCC recently completed (2) previous projects at this facility including a new influent pump station, headworks building, and UV system. Once this project is complete, the WWTP will essentially be a completely new facility.